WIND - an intelligent way of using the world's endless potential

Site Activity Updates

April 15th 2021
During the month of March, works continued on the scrapping of the tower sections. Civil works were ongoing related to access roads, removal of foundations and site restoration

March 15th 2021
During the month of February, works resumed following alteration in restrictions due to COVID-19. Civil works on site continued thereafter, and activities commenced related to the scrapping of the tower sections.

February 15th 2021
During the month of January, civil work began, including but not limited to: site preparation, mobilization, and demolition.  Some of these works were halted due to the Ontario lockdown, but will resume when legislation allows.

January 15th 2021
During the month of December, removal of the tower components of the turbine equipment was completed. No civil works were started.

December 15th 2020
During the month of November, removal of the tower components of the turbine equipment was commenced. No civil works were started.

November 15th 2020
During the month of October, removal of certain components of the turbine equipment was commenced. No civil works were started.

October 15th 2020
During the month of September, other than limited maintenance activities for equipment,  the site remained on standby.

September 15th 2020
During the month of August, other than limited maintenance activities for equipment,  the site remained on standby.


August 15th 2020

During the month of July, other than limited maintenance activities for equipment,  the site remained on standby.

July 15th 2020

During the month of June, a review of the current condition of the relevant Municipal Roads in the County of Prince Edward was conducted to prepare for further decommissioning activities.Otherwise,the site remained on standby. 


June 15th 2020

During the month of May, the site remained on standby due to COVID-19 restrictions.


May 15th 2020

During the month of April, the site remained on standby due to COVID-19 restrictions.


April 15th 2020

During the month of March, the site remained on standby due to half-load conditions and impacts of COVID-19 restrictions


March 15th 2020

During the month of February, the site was kept on standby during half load restrictions within the County.


February 15, 2020- During the month of January, the last of the crane equipment was packed up and removed from site, and maintenance was completed on the turbine components in the laydown positions.


January 15, 2020 – During December, the last of the towers and nacelles were moved into laydown positions. The crane equipment was disassembled and put in standby for pick up.


December 15th, 2019-  During November, crane equipment was erected at the Project Location to commence the decommissioning of the erected Turbines and Towers. All remaining towers to be in laydown locations on site before end of December..  


November 15, 2019 – During October, wpd White Pines Wind Incorporated commenced decommissioning activities and preparatory works on private lands, including installation of the storm water management measures, and the arrival of certain crane components.


October 15, 2019 – wpd White Pines Wind Incorporated submitted the monitoring report required under the regulation to Ministry of the Environment, Conservation and Parks and Prince Edward County. Notice of intent to recommence works was delivered to Prince Edward County.